CM YS Jagan reviews on Kadapa steel plant, allocates Rs. 500 crore under equity
CM Jagan discussed the proposals made by the companies. Officials were asked to hold talks with the companies that made the proposals. While the officials have asserted Chief Minister YS Jagan Mohan Reddy that they are planning to enter into a contract with the selected partner within two months. Also they said that it was decided that the township and adjoining infrastructure would be set up in two years. "Soil testing and geotechnical survey will be completed by the end of this month, officials said," officials said.
Officials explained that all necessary steps will be taken to complete the construction of roads, compound wall, power supply for the construction of the factory, as well as water for the factory maintenance.